see below for definitions |
Integration Planning |
1 3-5 3-5 1 |
On-campus integration planning Initial SIS data validation Submit integration planning form |
TD, FL, F (ITL, IT) FL, ITL FL, ITL FL or ITL |
Project kickoff meeting |
1 |
|
TD, FL, F, ITL, IT: all |
Custom URL set up |
0.5 0.5 1 |
Provide CSR information Provide SSL certificate |
IT: Network Admin IT: Network Admin IT: Network Admin |
SSH connection set up |
1 0.5 |
Public IP address(es) for whitelist |
IT: System Admin IT: System Admin |
Data file set up |
7
5 2 1 |
Program SIS file and provide sample file Update SIS file in response to TD feedback Complete Mappings Template Set up job to automate nightly file generation |
FL, F, ITL, IT: SIS Programmer IT: SIS Programmer IT: SIS Programmer FL, ITL, IT: SIS Programmer IT: System Admin |
Authentication set up |
2 1 |
Provide working test user credentials |
IT: Authentication IT: Authentication |
Testing |
1 1 5 |
Review production site settings Anonymized SIS data testing on Sandbox |
TD, FL TD, FL TD, FL, F |
Data validation |
Ongoing |
|
FL, F, ITL, IT: SIS Programmer |
Actors:
- TD = Terra Dotta
- FL = Functional Lead
- F = Functional users
- ITL = Campus IT Lead
- IT = Campus IT